  BALANCE WORK PENDING AT ATHUR ESWARAN KOVIL AS ON 15/10/05    
                   
SLNO  AREA      Material     value Labour(Approx) TOTAL
1) WALL COMPOUND PENDING   Cement required       10Bags 1500.00 1500.00 3000.00
  AT ONE  SIDE   Bricks   9000nos 13500.00   13500.00
                  16500.00
                   
2) PILLAYAR,MURUGAR,AMMAN  FOOT PATH FILLING      
        Cement required 75 Bags  11250.00 3000.00 14250.00
                   
                   
3) Durgai     Cement required 10bags 1500.00 1000.00 2500.00
        Steel 6mm 10kgs &10mm 50kgs 7020.00   7020.00
                  9520.00
                   
4) NANTHI     Cement required      10 bags 1500.00 1000.00 2500.00
        (ie Roof, pillar cement filling)      
                   
5) ALANGARA MANDABAM Cement required      10bags 1500.00 1000.00 2500.00
        (ie Roof work,        
        Side wall cement filling       
                   
6) NAVAGIRAGAM   Cement required    15bags 2475.00 1000.00 3475.00
                   
                   
                   
7) WELL  INSIDE CEMENT  Cement required 10Bags 1500.00 1000.00 2500.00
  FILLING                
                   
8) MADAPALI   Cement required  30bags 4950.00 2000.00 6950.00
                   
9) WHITE WASH          20000.00 20000.00 40000.00
                   
10) ELECTRICAL COMPLETE WIRING     10000.00   10000.00
                   
11) GRANITE AT MOOLASTHANAM     60000.00 10000.00 70000.00
 
                   
12) PASTING & ACID CLEANING AT MOOLASTHANAM   2000.00 6000.00 8000.00
 
          TOTAL---------------------------------------------------------- 186195.00

Contact

B.RAGHAVAN,
NO 45, REDDY STREET, ATHUR VILLAGE &POST, KANCHEEPURAM DIST, PIN 603 
101.
matlrag@vsnl.net

Renovation Estimates

See Above.

Back to thirupaNi page
Back to Shaiva Siddhantha Home Page
Back to Shaivam Home Page